Day 59
Door and gate installation.
Day 58
Moving day. KNT movers did a great job.
Day 55
Carpentry painting, vinyl flooring works and cleaning.
Day 53
Carpentry finishing up works and Quartz installation.
Day 52
Carpentry installation continues.
Day 49
Air-con unit installation and sanitary appliances installation.
Day 45
Painting done, installing kitchen door, minor tiling works and carpentry in progress.
Day 44
Lighting installation continues and automatic laundry pole installed.
Day 43
As with all HDB flats, most walls are not flat. Due care was taken to plaster the rest of the walls that is exposed to allow the painting...
Day 42
Shower box-up wall construction in progress. Carpentry works work progress update and painting for ceiling done.