Day 28
Window grilles are installed for living, bedroom and master bedroom. Kitchen floor is screeded in preparation for floor tiles to be...
Day 25
Tiling works in progress, tiles in master bath done and kitchen wall tiles in progress. After this they will proceed with working on the...
Day 21
Ceiling works have to stop as they need the tiling works to finish before they can come back and cover up everything. Floor is being...
Day 21
Mi Smart Home parts just arrived, can't wait to test them out. What I really love about them is that I can always add onto the system by...
Day 19
Ran into some problems with the existing plumbing main stack. They are quite old and leaking. Called town council and they recommended me...
Day 17
Windows installation day. Windows have to come in before the bath room tiles work are done so that the tiles can finish nicely before the...
Day 15
Previously roughen walls are now cement plastered. Ceiling & wall framework in progress and some parts are already being covered by the...
Day 11
Most of the debris are cleared. Existing wall tiles are hacked away and smooth walls roughen by making small holes.
Day 7
Stage 2 of demolition works. Bedroom wall hacked to create more space in the living room. Kitchen wall hacked to reduce the kitchen size...
Day 3
Demolition work starts today. All the built-in cabinets are removed and disposed.