Day 44
Lighting installation continues and automatic laundry pole installed.


Day 43
As with all HDB flats, most walls are not flat. Due care was taken to plaster the rest of the walls that is exposed to allow the painting...


Day 42
Shower box-up wall construction in progress. Carpentry works work progress update and painting for ceiling done.


Day 40
Carpentry installation and painting works in progress.


Day 37
Kitchen wall panels are up and preparing to start painting works tomorrow.


Day 34
Plumbing works in progress to lay hot and cold water pipes. Kitchen and bath concrete base done.


Day 33
Kitchen flooring done, next is doing the concrete base. Major piping works for plumbing and air-con drainage done.


Day 28
Window grilles are installed for living, bedroom and master bedroom. Kitchen floor is screeded in preparation for floor tiles to be...


Day 25
Tiling works in progress, tiles in master bath done and kitchen wall tiles in progress. After this they will proceed with working on the...


Day 21
Ceiling works have to stop as they need the tiling works to finish before they can come back and cover up everything. Floor is being...